Basic Info.
Model NO.
GreenFirLNG
Condition
New
Certification
ISO, GB ASME
Type
LNG Production
Flow
1 Mmscfd to 50 Mmscfd
Inlet Pressure
100 Psi
LNG Output
50 Tons Per Day
Main Equipiment
Compressor, Cold Box
Process
Mixed Refrigeration
Product
LNG LPG Ngl
Transport Package
Suitable for Sea Transportation
Trademark
Greenfir
Origin
China
Product Description
DESCRIPTION:
Natural gas liquefaction plant, LNG production Plant
Process: MRC
Turndown ratio: 30%-110%
Capacity: 72000Nm3/day @Ps=30~60barg,Ts=15~30°C
LNG output: 67440Nm3/day (ie, 2810Nm3/h or 50.88TPD)
Power consumption: 2.1 MW
Cryogenic compressor: screw compressor
NG compressor: Without NG booster compressor
LNG storage capacity: 2×500m3 (10 days' backup ststem)
LNG temperature: about -160°C
Natural gas liquefaction plant, LNG production Plant
Process: MRC
Turndown ratio: 30%-110%
Capacity: 72000Nm3/day @Ps=30~60barg,Ts=15~30°C
LNG output: 67440Nm3/day (ie, 2810Nm3/h or 50.88TPD)
Power consumption: 2.1 MW
Cryogenic compressor: screw compressor
NG compressor: Without NG booster compressor
LNG storage capacity: 2×500m3 (10 days' backup ststem)
LNG temperature: about -160°C
After gas-liquid separation, the natural gas from the user is sent to the purification device. The purified natural gas
enters the low-temperature cooling and distillation unit for distillation, and C3+recovery is carried out in the
deethanizer tower. After cooling by the top gas phase return plate heat exchanger, LNG is obtained. The liquid
phase at the bottom of the tower is pumped into the debutanizer tower. Obtain qualified LPG and NGL products in